Monday, November 15, 2010
Stairs are Finished
The front stairs are completed except for the railing which we have to think about what we want. The area around the stairs has been seeded and straw has been added.
A side view of the stairs.
Top view, the stone around the platform and the steps are granite and the risers and sides are field stone.
Here is a photo of the work in progress.
Thursday, November 11, 2010
Front Porch Construction
Wednesday, November 10, 2010
Porch and Garage
A lot of work is being done this week, not only the garage but the work has been started on the front porch and stairs. Here the hole is being dug for the footings.
The hole is dug and is ready for the footings to be poured. Somehow I didn't get a photo of the poured footing but it can be seen in other photos.
Blocks are being added as a base for the platform and stairs.
After building the block frame, it is filled with crushed stone.
Work continues on the garage. The beams are all on the roof.
The side wall is almost done also. Tomorrow, sheeting should be on and will be ready to shingle.
Sunday, November 7, 2010
Garage Day Five
Tuesday, November 2, 2010
Garage Day Four
Monday, November 1, 2010
Garage Day Three
Subscribe to: